Issue
Many kinds of electrical systems, from lighting and outlets to nurse call and fire safety equipment, had to be installed in step with the building schedule.
Action
Before construction began, we gave the general contractor value engineering (VE) proposals to lower the cost of the main feeders and low-voltage systems. On site, we kept our schedule in step with SOWA SERVICE, which handled the mechanical systems.
Result
Construction began in November 2021, and the work was completed in May 2022.